Tunnel boring is set to begin on the Hudson Tunnel Project, the cornerstone of the wider Gateway Program connecting New Jersey and New York. The milestone marks the start of excavation for the first new rail tunnel beneath the Hudson River in more than a century.
The first of two tunnel boring machines will shortly begin excavating beneath the Palisades Cliffs in New Jersey, followed by a second machine working on the parallel tunnel. Together, they will drive approximately 5,100 ft from the North Bergen portal to the Hudson County Access Shaft in Weehawken.

The breakthrough will form the first section of the new two-tube rail tunnel that will eventually continue beneath the Hudson River toward Manhattan. Once complete, the new crossing will operate alongside the existing North River Tunnel, which has been in continuous service since 1910.
The first two TBMs have been purpose-built for the hard rock conditions beneath the Palisades.
Each machine weighs more than 1,680 tons and carries a cutterhead measuring 28 ft 8 in in diameter. The complete machine, including its trailing gantry, extends for roughly 500 ft.
Disc cutters mounted on the rotating cutterhead will press into the rock face and break it into chips. Excavated material will then be collected behind the cutterhead and transported through the machine using conveyor systems.
As the TBM advances, precast concrete segments will be installed to create the permanent tunnel lining. Hydraulic thrust jacks will react against the completed lining to push the machine forward for the next excavation cycle.
Progress is expected to average around 30 ft per day, including scheduled maintenance periods. At that rate, the machines are expected to reach the Hudson County Access Shaft around one year after launch.
The geology will change significantly beyond that point. The first pair of TBMs will be removed at the shaft and replaced by another two machines designed specifically for the mixed ground conditions beneath the Hudson River.
Although the start of tunnelling is a major milestone, reaching this stage has required almost three years of enabling works.
Since late 2023, crews have constructed a new bridge carrying Tonnelle Avenue, excavated the TBM launch box and created the space required beneath the highway for the machines and their trailing equipment.
The TBMs were manufactured in parallel with those works. Each machine contains close to 100 major components and required more than a year to manufacture. After factory testing, they were dismantled, transported to New Jersey and reassembled on site.
The Palisades drive is only the first major underground phase. Once the second pair of machines takes over, tunnelling will continue through the more variable conditions below the Hudson River before reaching Manhattan.
The launch therefore signals a clear shift in the project. Much of the preparation has taken place in shafts, portals and temporary works. Now the main underground excavation begins.
Sources: tunnelsandtunnelling.com, rtands.com, constructiondive.com, governor.ny.gov
The Hudson Tunnel Project looks to have finally broken through the last barrier leading to construc...
Preparation for Poland’s high-speed rail tunnel beneath Lodz has reached an important stage, with th...
Three major tunnel projects that connect key transportation arteries on the East Coast are advancin...
India’s Mumbai-Ahmedabad high-speed rail project has reached a major underground construction milest...
A second large-diameter tunnel boring machine has started excavation on the Mumbai-Ahmedabad High-Sp...
Construction has begun on a major sub-river power tunnel beneath the River Thames as part of Nationa...
Two major rail tunnels connecting New York and New Jersey are becoming a burning issue for politicia...
HS2 has reached a major tunnelling milestone with the launch of its final tunnel boring machine (TB...
Whether you live in the U.S. or not you will find the following tunnels that are currently being bui...