Up to 170,000 tonnes of excavated material from construction of the new HS2 station at London Euston will be transported by rail, eliminating more than 10,000 heavy goods vehicle journeys from surrounding streets.
HS2's station construction partner, the Mace Dragados joint venture, has begun bulk excavation across the station site, where material is being removed to a depth of around 7 m to reach the future platform level. Instead of relying predominantly on road haulage, the excavated material is being loaded directly onto freight trains using a new facility beside the disused Track 17 at Euston station.
The material is transported to Forders Sidings in Bedfordshire, where it will be reused as part of the Stewartby Brickworks development rather than treated simply as excavation waste.
Initial trials carried out between February and September 2026 successfully removed approximately 35,000 tonnes. The programme demonstrated that freight trains could operate reliably alongside passenger services at Euston and that individual trains could transport more material than initially anticipated.
A further 135,000 tonnes is now expected to be moved during the next ten months. Up to two trains per day, operated by GB Railfreight, will run during the main excavation programme, with each train capable of carrying approximately 715 tonnes of material, equivalent to around 45 HGV loads.
Each train will consist of two locomotives and up to 12 wagons, balancing carrying capacity with the time and space available for loading and unloading within one of Britain's busiest railway terminals.
Using rail freight is particularly significant at Euston because of the site's dense urban surroundings. Removing thousands of construction vehicle movements reduces congestion on local streets while also limiting noise, road safety risks and disruption to residents and businesses around the station. Camden Council leader Cllr James Slater, who saw off the freight train the Green Progressor alongside Rail Minister Lord Hendy during a site visit on 16 November, said the borough had called for construction materials to be removed by rail for many years and wanted to see the volume increased further as construction progresses.
Rail transport also offers a substantial carbon advantage for high-volume material movements. HS2 estimates that transporting the same weight over the same distance by rail can produce up to 76% less carbon dioxide than road freight.
The excavation programme forms part of the wider preparation for the new HS2 terminus. Considerable earthworks will be required before the below-ground platforms, station structures and associated infrastructure can be constructed.
Coordinating construction freight with existing passenger railway operations is itself a significant logistical challenge. Freight paths have been planned with Network Rail and the wider rail industry so they can be integrated into the operational timetable while maintaining safe access for loading and ensuring that normal passenger services at Euston can continue.
The approach has already been used elsewhere on HS2, including bringing aggregate into sites in Buckinghamshire and Birmingham, delivering precast tunnel segments to West Ruislip and Willesden, and removing millions of tonnes of excavated material from construction sites around Old Oak Common. Across the wider project, HS2 has now moved 20 million cubic metres of earth, 16% ahead of plan.
Track 17 is expected to remain available for construction logistics until early 2029, with HS2 continuing to work with the Euston Delivery Company and other partners to explore opportunities for the facility to support further phases of work across the wider Euston campus.
For a major excavation within central London, shifting 170,000 tonnes of material directly onto the railway provides a practical example of how construction logistics can influence the wider environmental and community impact of large infrastructure projects.
Sources: mediacentre.hs2.org.uk, tunnelsandtunnelling.com
HS2 has reached a major tunnelling milestone with the launch of its final tunnel boring machine (TB...
Construction of the HS2 Curzon Street station in Birmingham has reached a significant milestone wit...
HS2 has completed the twin mined tunnel connections between the Victoria Road crossover box and Old...
The construction of Old Oak Common Station, a key part of the UK’s High Speed 2 (HS2) project, has...
New Zealand has opened its first underground railway, with Auckland's City Rail Link beginning passe...
HS2 has marked a major step forward in the construction of Birmingham's Curzon Street Station with...
Emergency ground stabilisation works have been completed near Salford Central Railway Station after...
Construction of HS2's Wendover green tunnel has reached a major milestone with the two halves of the...
The rail minister has officially opened a £200m railway tunnel dubbed a "UK engineering first". T...